Kent Facilities at Its Best: Industrial Facility Improvements for ANDRITZ BCN

Facility improvements can get complicated quickly. Kent Facilities believes it doesn’t have to. During the first site walk at ANDRITZ BCN’s future West Michigan headquarters to price 38 concrete pads and a compressor room to the building footprint, the owner pointed to existing warehouse shelving.

Do you know someone who could remove that?

Our answer was yes. Us. 

Removing and packaging the racking became one of the first steps in preparing the former Aspen Surgical facility for ANDRITZ BCN. More importantly, that exchange set the tone for the relationship that followed. When a need came up, Kent Facilities found a way to help. 

Facility Improvements Built Around the Customer

From there, more questions followed.

Could Kent Facilities make the building modifications needed for the new crane access? Yes.

Could the team construct a new compressor room? Yes.

Could they modify existing overhead door openings to accommodate larger doors? Yes.

And when ANDRITZ BCN decided midway through the project to add a shipping office within the warehouse? Yes again. 

“We got this opportunity through a referral, and we don’t take that for granted,” explains Division Manager Jeff Moomey. “That’s the value of having a versatile team. We can take on a wide range of needs, do the work well and keep things moving. We believe that kind of service is what brings customers back—and what makes them comfortable recommending us to someone else.”

A Growing Scope of Industrial Facility Improvements

The original crane pad scope expanded into improvements throughout the facility. In total, Kent Facilities:

  • Removed and packaged existing warehouse racking.
  • Installed 38 crane pads for two overhead cranes and four jib cranes, including removal of the existing six-inch floor, excavation, reinforcement and concrete placement.
  • Modified the existing CMM room and warehouse for crane access, including a 12-foot by 14-foot wall opening, raised ceiling area, and associated HVAC, lighting and fire suppression modifications.
  • Constructed a new exterior compressor room, including foundations, slab-on-grade, structural steel stud framing, insulated metal panels, interior finishes and fire suppression.
  • Enlarged two existing overhead door openings from 12 feet by 14 feet to 14 feet by 16 feet, requiring modifications to the existing foundations, structure, insulated panels, concrete drives and bollards.
  • Completed office improvements, including removing 18 existing cubicles and constructing a new electric fireplace in the president’s office.

The 15-foot by 45-foot shipping office was added midway through the project, after Kent Facilities had become familiar with the building and ANDRITZ BCN’s operation. The team incorporated the new space into its work, completing the steel stud partitions, dust-cap joist system, doors, windows, ceilings, lighting and fire suppression. 

“As the project progressed and things came up; I knew I could bring them to the team and they’d help find a solution. They understood what we were trying to accomplish, were responsive when things changed and became a team we knew we could count on,” said ANDRITZ BCN Business Development Manager Cody Newton. 

Making Facility Improvements Easier

The final scope at ANDRITZ BCN reflects Kent Facilities at its best. A versatile team, a growing customer relationship and a shared focus on finding solutions as new needs emerged.

Buildings are constantly changing, and the next need isn't always part of the plan. Sometimes it's a crane foundation. Sometimes it's a door opening. Sometimes it's shelving that needs to disappear.

Facility owners and managers shouldn’t have to start from scratch every time. That’s the value of a relationship with Kent Facilities—and exactly the kind we're built to create.

Have something in your facility that needs to get done? Start with Kent Facilities.

Kent Nov23 Hastings 20

Latest News

Profile

Growing the Pipeline: Fall Career Fair Season Kicks Off

Kent is heading back to campus this fall to meet the next generation of builders and grow the talent pipeline supporting our continued expansion across the country.

Profile

Growing Through Feedback: A Kent Intern’s Perspective on Mentorship

Marketing Intern and Aquinas College Student Michelle VanWeelde takes over the blog to share her perspective on how feedback guides growth.

Profile

Project Highlight: Sennebogen – Stanley, NC

Advanced manufacturing facilities demand concrete construction that supports tight tolerances and complex building systems.